Provincial shortcomings delay campus child care

UBC says the project was dependent on the ChildCareBC New Spaces Fund. Still, parents say the university should've been more proactive.

A photo of the Orchard Commons Residence

"I wish that there were more [child care] spaces, and I wish that families weren't undergoing this," said lecturer and mother Anna Dawczyk.

Aleah Kippan / The Ubyssey

Construction of a UBC child care centre has been delayed for 17 months, with no official estimate for when it will begin. UBC says it is waiting on provincial funding.

UBC Child Care, an early education provider under Student Housing and Community Services, manages 30 on-campus child care sites with about 750 children enrolled. SHCS is a "self-funded ancillary unit" within UBC's Vice-President, Students portfolio that provides "essential services and resources" to the UBC community.

The centre's budget was $5.75 million, according to a 2023 Board of Governors document. That document estimated $3.5 million, about 61 per cent, would come from the provincial New Spaces Fund, pending provincial approval. The rest was to come from internal loans: $1.75 million from SHCS and $500,000 from the Sauder School of Business, which had committed funding to child care as part of its own expansion project. The two were to split any shortfall equally.

The Board's Property Committee considered a request on Sept. 13, 2023, to approve the development of a child care centre beside Orchard Commons. The request listed a preliminary capital budget of $5.75 million and an accommodation limit of 28 children, with construction slated to start in April 2025.

Seventeen months after that planned start date, though, construction has yet to begin.

Until Sept. 22, the UBC Campus + Community Planning website still said construction would begin in April 2025. UBC Child Care's "About Us" webpage also said it was "pursuing the development of a purpose-built, 28-space child care setting next to Orchard Commons student residence, which [they] hope to open in 2026."

The Ubyssey asked UBC media relations about the statements on Sept. 22, and both websites were updated the next day. The April 2025 start goal was replaced with "TBD," and the 2026 opening date was deleted. The About Us page now says "construction of this project will begin once funding is secured." With only three months left in 2026, the project is still not in development.

In a statement to The Ubyssey, Karen Vaughan, director of UBC Child Care Services, said the university "anticipated support from the ChildCareBC New Spaces Fund" when creating the project's budget. The fund is "a provincial program that provides funding to public sector organizations, including public post-secondary institutions, to create new licensed child care," Vaughan said.

The New Spaces Fund has been paused since February 2026, according to the province, leaving the university unable to secure funding for the Orchard Child Care Centre. Vaughan said the fund "has supported construction of 37 child care spaces at Brock Commons, 98 spaces at Salmo and Revelstoke Courts, and 37 spaces in Wesbrook Place."

According to the B.C. government's website, the fund was paused pending a "review and retool" of ChildCareBC as a whole because "some elements of the system are not working as intended." ChildCareBC was introduced in 2018 as a social program dedicated to "building a future where access to affordable, quality, inclusive child care is a core service that families can depend on."

With construction on hold until funding is secured, Graduate Student Society (GSS) President Hayley Lawrence suggests UBC consider allocating some of its own budget to the centre, or put more pressure on the government for funding.

Lawrence added that it is "really important" for graduate students with children to be able to access on-campus child care. "It's really convenient when people live on campus and they're able to access child care, because it means they don't have to go somewhere else to take the child there, and then come back to campus for classes or work."

UBC sociology lecturer Anna Dawczyk said in an interview that on-campus child care "is a very, very common topic among many, many parents who have young kids."

Dawczyk has three children. Her eldest was on the UBC daycare waitlist for two years before getting a spot when he turned three, and her twins were on the waitlist for two and a half years before getting a spot when they turned two.

According to the UBC Child Care Services website, the average wait time for parents with children under 12 months old is "typically nine months to 15+ months old." However, "the majority of these spaces are filled by children with sibling priority status." The wait time for UBC students, faculty, and staff with a 12- to 36-month-old child is two to 2.5 years. For UBC parents with children aged 2.5 years to kindergarten, it is one to 2.5 years or more. Dawczyk was told the chance of getting off the waitlist increases once a child turns 3.

"It's really tough on families," Dawczyk said. "I wish that there were more [child care] spaces, and I wish that families weren't undergoing this, especially families who are low income or people who have young kids who absolutely desperately need childcare."

Dawczyk said the Orchard Child Care Centre's delay is "really unfortunate," and should have been "openly communicated to people involved in UBC," but added that "construction is complicated" and "often delayed."

UBC alum Neola Husbands said the university was not "completely transparent" about the delay. Husbands spent 10 years living on campus and raising her now 8-year-old son while studying for her degree. When she found out she was two weeks pregnant, she immediately put him on the waitlist for UBC Daycare, but he was not given a spot until he was 18 months old.

Inspired by her experience navigating UBC's child care system and battling the rising cost of living in Vancouver, Husbands is launching an app in Vancouver called Neola in September 2026. She describes it "as an online platform that connects parents who are on the go ... with people that are willing to show up ... have their back, and make some extra money."

Husbands said UBC should have understood "that there are people that are genuinely waiting for this [centre]," and should have been transparent about the funding issues and delayed timeline.

"[When] it takes a journalist to investigate and go see that the space is still empty and ask questions — that's when it becomes a problem," Husbands said. "I think it's really unfortunate for the parents because ... 28 spaces is not a lot, but I would die for 28 extra spaces to pop up in front of me, knowing that my name can be [on] one of them."

Husbands understands that from a university revenue perspective, it makes sense to "get as much funding as [UBC] possibly can from outsources." She added that if UBC shows it has money in the budget to fund the centre itself, the province may not agree to fund future UBC Child Care projects.

As a parent, though, she doesn't care about UBC's finances. "I am focusing on that extra study group that I can't get to, or that assignment that I cannot put my 100 per cent in, or even that extra meeting that I have to show up to — but I know that I'm not all the way there because I desperately need child care."

"All I can see is a campus that is ever-evolving ... I see new outdoor spaces. I see new activities," Husbands said. "And all I can think of as a parent without child care is how much I do not get to be involved, and that is where ... it would break my heart." She added that it is "disheartening" that UBC has to depend so heavily on the New Spaces Fund.

Husbands said that "if UBC has the option, and I think they do," the university should invest in child care because "focusing on child care as a necessity and a priority can really change [the] trajectory for a lot of people on-campus."

Plans for on-campus child care in the Sauder School of Business Power House Expansion go back to at least March 2022. A Board 1 approval document dated March 16, 2022, mentioned having the expansion accommodate approximately 5,000 square feet of space "for two 25-space child care facilities to be operated by UBC Child Care Services." The $120 million project budget included $1.5 million for child care tenant improvements and landscaping.

The Sauder plan put the child care facilities on the third floor of a new tower. During schematic design, UBC decided the child care would be better delivered in a stand-alone building elsewhere on campus, according to a 2023 Board document. The project moved to the courtyard along West Mall in front of Orchard Commons. Sauder committed $500,000 toward the base building. Because of site constraints, the Orchard centre is planned for 28 spaces, short of the two 25-space groups planned at Sauder.

The Orchard Child Care Centre project currently includes a one-storey building and two fenced outdoor play areas. The centre is designed to accommodate 28 children, with 12 spaces for infants and toddlers and 16 spaces for 3- to 5-year-olds.

The centre is part of the UBC Vancouver Child Care Expansion Plan (CCEP), which was first released in 2009 and updated in 2018 and 2026. According to Vaughan, the CCEP "commits the University to expanding child care capacity in step with population increases, ensuring that families who live, study, and work at UBC have access to the services they need."

In the 2026 update, released April 30, UBC pledged to build 417 new child care spaces by 2050, a 40 per cent increase in on-campus capacity. The update also reported that "UBC met its 2018 CCEP five-year growth target to 2024, delivering 219 net-new spaces since 2018, resulting in a total of 1,033 child care spaces across campus."

Most recently, UBC Child Care opened the Nobel Park Child Care Centre in Wesbrook Place on April 15, adding 37 licensed spaces for children aged 0 to 5. The centre was supported by the New Spaces Fund.

Looking ahead, Vaughan wrote that "UBC is building a new 37-space child care centre not far from Orchard Commons as part of the Lower Mall Precinct Project." The project, which received $300 million in provincial funding according to Vaughan, began construction in August 2026. The child care centre is scheduled to open in 2028.

A previous version of this story stated that Anna Dawczyk is a professor. This was wrong — Dawczyk is a lecturer. The story was updated to reflect this correction October 5 at 9:54 p.m.

Apply for erasureSend a tipReport an error